Mayor Federico Pena and Adams County officials agree to build a replacement for Stapleton International Airport. Project estimate: $1.2 billion.
Denver voters pass airport referendum. Project estimate: $1.7 billion.
Mayor Wellington Webb announces first delay. Opening day postponed from October to December. Project estimate: $2.7 billion.
Opening pushed to March 1994; fire and security systems aren’t ready. Project estimate: $3.1 billion.
Now it’s the baggage system. Opening day delayed to May 15.
Webb says airport will miss fourth deadline.
Officials say they’ll float $225 million in bonds to finance a second baggage system and cover delays. Project estimate: $4 billion-plus. Opening date: TBA.